RTA opens two main bridges as part of Al Khail Road Development Project

80% of the works are completed in the project extending across seven sites

Al Tayer:

  • The project contributes to a 30% reduction in travel time
  • Works include constructing five bridges and lane-widening along Al Khail Road
  • The five bridges span 3,300 metres, with a capacity of 19,600 vehicles per hour
  • Widening works have been completed at two sites in Al Jaddaf and Business Bay

Dubai. Roads and Transport Authority. 1st September 2024

Dubai’s Roads and Transport Authority (RTA) has opened two major bridges at Zaa’beel and Al Quoz 1 on Al Khail Road in the direction of Jebel Ali. The completed bridges span 1,350 metres and have a combined capacity of about 8,000 vehicles per hour. RTA also announced that the completion rate has reached 80% in Al Khail Road Development Project, involving the construction of 3,300-metre-long bridges and the widening of lanes stretching over 6,820 metres.

These improvements spread across seven sites on Al Khail Road, covering Al Jaddaf, Business Bay, Zaa’beel, Meydan, Al Quoz 1, Ghadir Al Tair, and Jumeirah Village Circle. The project aims to reduce travel time by 30%, increase the capacity of existing intersections and bridges by 19,600 vehicles per hour, enhance traffic efficiency on Al Khail Road, resolve traffic overlaps at flyovers, and ensure continuous and smooth traffic flow.

His Excellency Mattar Al Tayer, Director General, Chairman of the Board of Executive Directors of RTA, stated: 'The project aligns with the directives of His Highness Sheikh Mohammed bin Rashid Al Maktoum, Vice President, Prime Minister of the UAE, Ruler of Dubai, to continue enhancing the road network infrastructure to support the ongoing development in the Emirate. Our goal is to accommodate the needs arising from urban development and population growth and to improve traffic flow, which is guided by the follow-up of His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, Deputy Prime Minister, Minister of Defence.'

'Al Khail Road Development Project is a key strategic project aimed at developing parallel and supporting road corridors to Sheikh Zayed Road, Sheikh Mohammed bin Zayed Road, and Emirates Road. Al Khail Road is a major arterial road in Dubai, extending from the Business Bay Crossing to its intersection with Sheikh Mohammed bin Zayed Road. It consists of five lanes in each direction, expanding to more than six lanes in some sections,' Al Tayer commented.

Opening of Two Bridges

“The first bridge opened is located at Zaa’beel. It connects traffic from Zaa’beel Palace Street and Oud Metha Street to Al Khail Road towards Jebel Ali. This 700-metre-long bridge has three lanes and a capacity of 4,800 vehicles per hour. The second bridge opened is located at Al Quoz 1. It links traffic from Al Meydan Street to Al Khail Road towards Jebel Ali. This two-lane bridge extends 650 metres and has a capacity of 3,200 vehicles per hour,” Al Tayer added.

Sites 1 and 2

“The project includes improvement works at seven sites along Al Khail Road. Site 1 is in Al Jaddaf and involves surface expansion works by adding a new lane to improve traffic flow towards Deira. It increases the road’s capacity in the sector between the intersections of Oud Metha Street and Financial Centre Street by 2,000 vehicles per hour. Works also include the construction of a three-lane bridge extending 700 metres with a capacity of 4,800 vehicles per hour, connecting traffic from Zaa’beel Palace Street and Oud Metha Street to Al Khail Road towards Jebel Ali. Additionally, works include surface road improvements over 850 metres to link traffic from Al Khail Road to Financial Centre Street towards Sheikh Zayed Road,” Al Tayer explained.

“Site 2 at Meydan area on Al Khail Road is located between the intersections of Al Meydan Street and Ras Al Khor Street. works include the construction of a two-lane bridge, 610 metres long, with a capacity of 3,200 vehicles per hour, connecting traffic from Meydan Street to Al Khail Road towards Deira. Works also involve surface road improvements over 1,550 metres to connect traffic from Al Khail Road towards Ras Al Khor Street,” he added.

Sites 3 and 4

“Site 3 is  in Al Quoz 1 on Al Khail Road between the intersections of Al Meydan Street and Al Waha Street. Works involve the construction of a two-lane bridge, 650 metres long, with a capacity of 3,200 vehicles per hour to connect traffic from Meydan Street to Al Khail Road towards Jebel Ali. Works also cover surface road improvements over 2,170 metres to connect traffic from Al Khail Road to Al Waha Street and Latifa Bint Hamdan Street,” said Al Tayer.

“Site 4 is at Ghadir Al Tair on Al Khail Road between the intersections of Al Meydan Street and Latifa Bint Hamdan Street. Works include constructing a two-lane bridge, 640 metres long, with a capacity of 3,200 vehicles per hour to facilitate traffic from Latifa Bint Hamdan Street to Al Khail Road towards Deira. Works also include surface road improvements over 1,350 metres to link traffic from Al Khail Road to Al Meydan Street,” noted Al Tayer.

Site 5

“Site 5 is at Jumeirah Village Circle on Al Khail Road between the intersections of Hessa Street and Al Khamila Street. Works involve constructing a two-lane bridge, 700 metres long, with a capacity of 3,200 vehicles per hour to connect traffic from Al Khail Road to Hessa Street. Works also include surface road improvements over 900 metres to link traffic from Jumeirah Village Circle to Al Khail Road towards Deira,” concluded Al Tayer.

Work Progress

Last May, RTA completed the widening works at Site 6 and Site 7 in Al Jaddaf and Business Bay. At Site 6, works included surface expansion of Al Khail Road at Al Jaddaf by adding a new lane to improve traffic flow towards Deira over a 600-metre stretch, increasing the road’s capacity by 2,000 vehicles per hour. Works at Site 7 involved surface expansion of Al Khail Road at the entrance to Business Bay by adding a new lane, 435 metres long, to enhance traffic flow towards Business Bay from Al Khail Road and improve traffic safety in the direction of Jebel Ali. According to the plan, three bridges will open at three locations by the end of this October, serving traffic towards Deira.

Captions:

  • Mattar Al Tayer
  • Layout of Al Khail Road Development Project


Posted by : DubaiPRNetwork.com Editorial Team
Viewed 11332 times
PR Category : Local News and Government
Posted on : Monday, September 2, 2024  9:43:00 AM UAE local time (GMT+4)
Replication or redistribution in whole or in part is expressly prohibited without the prior written consent of DubaiPRNetwork.com.
Previous Story : Dubai Fitness Challenge 2024 Dates Are Here! Block Your Dia...
Next Story : World champion leads Team Abu Dhabi 1-2 and has perfect chan...
Email this article Print this article

Share this article with your friends and followers
NewsVine
 
 
Most Viewed Press Release posted in the last 7 days
Sita and nec collaborate to drive global adoption of digital identities in travel [44456-Views]
IATA Aviation Day MENA to Focus on Collaboration, Innovation and Harmonization [41697-Views]
Saudi Arabia to showcase record tourism growth at ATM 2025, marked by a 16% increase in ex... [24871-Views]
e& UAE redefines 5G with 6 GHz and 600 MHz testing, achieving premium speed and coverage [19791-Views]
Titan unveils the first International multi-brand lifestyle destination store in UAE [19270-Views]
IATA Launches FACE Ambassadors Program to Attract Next Generation of Air Cargo Talent [17987-Views]
UAE and Türkiye Forge Stronger Economic Ties at 2nd Joint Economic and Trade Commission (J... [15588-Views]
Emirates Park Zoo & Resort in Abu Dhabi to support rescue and rehabilitation of endangered... [15326-Views]
Danube Properties Celebrated Early Completion of Third Consecutive Project with a Grand Ei... [13042-Views]
Sorbonne University Abu Dhabi Celebrates the Nation's Rich Heritage with ‘Threads of Herit... [12484-Views]
Etihad Reports March 2025 traffic Statistics [11997-Views]
IATA Launches Information Portal for Live Animal Regulations [11082-Views]
UAE, Ireland sign MoU to Enhance Economic and Technical Cooperation and the establishment ... [11000-Views]
Etihad airways unveils new route to peshawar, pakistan [10791-Views]
Collection De L'atelier Blooms Again [10164-Views]
Experience Abu Dhabi this April with Unmissable Concerts, Festivals and Entertainment [9959-Views]
Strategic Development Fund and QuantCube Technology Launch Joint Venture to Support the Gr... [9102-Views]
The UAE Lottery Celebrates Big Wins for Lebanese and Colombian Players [9073-Views]
Bollywood Star Kareena Kapoor Khan to Inaugurate Malabar Gold & Diamonds' Stunning New Sho... [9073-Views]
EGA launches season three of Ramp-Up to foster the next generation of UAE entrepreneurs [8950-Views]
Sheikh Nahyan Mubarak Al Nahyan Inaugurates World Crisis and Emergency Management Summit 2... [8889-Views]
Gold (XAU/USD) drops sharply amid market panic, but fundamentals remain strong [8754-Views]
HE Al Zeyoudi Highlights UAE's Commitment to Advancing Global Trade and Investment Partner... [8548-Views]
World Champion Tadej Pogačar Targets Historic Paris-Roubaix Victory [8446-Views]
João Almeida places second in Itzulia Basque Country opener [8196-Views]
 
RSS Facebook Twitter LinkedDin DubaiPRNetwork.com on Instagram
 
Back to Section Home

Related Stories

 
Top Sections
 
Top Stories